WBSEDCL to set up a pumped storage facility at Purulia

first_imgCOMMENTS Published on SHARE COMMENT November 15, 2018 power and distribution West Bengal State Electricity Development Corporation Ltd (WBSEDCL) will set up a 1000MW pumped storage facility at Ayodha Hills in the Purulia district of the state at an estimated cost of Rs 6,922 crore. The Japan International Cooperative Agency (JICA) will provide a loan assistance of Rs 5000 crore for the project. The loan agreement with JICA was signed on November 2.According to a release issued by WBSEDCL, the project will have four reversible pump turbine units of 250 MW each. West Bengal SHARE SHARE EMAILlast_img